Cathedral Center Construction


Aerial view of Cathedral Center Property prior to construction















Center Progress.
The final section of the floor
will be poured on Monday, May 4. The
parapet will be completed... metal studs for
the translucent panels on the upper roof will
continue... studding for interior partitions
and dry wall on the concrete block in the main
hall will begin... vent work will begin...progress
continues...